How Do You Read a P and ID in Oil and Gas? A Practical Guide for Beginners

A P and ID can look ridiculous the first time you see one.

There are lines everywhere. Circles contain letters. Valves have different symbols. Some lines are solid, others are broken. Equipment has numbers attached to it, and half the drawing seems to disappear onto another sheet.

Then someone who has worked at the plant for twenty years looks at the same drawing for ten seconds and immediately knows where the problem is.

Reading a P and ID is not really about memorizing hundreds of symbols. It is about learning how to trace a process logically.

Once that clicks, the drawing starts looking less like a page of symbols and more like a map of the facility.

What Does P and ID Mean?

P and ID means piping and instrumentation diagram.

It is a schematic drawing showing how process equipment, piping, valves, instruments, and controls are connected.

>

You may see:

Separators

Pumps

Compressors

Heat exchangers

Storage vessels

Control valves

Pressure transmitters

Level transmitters

Flow meters

Temperature instruments

Relief valves

Drains

Vents

Sample connections

Shutdown valves

The important word is schematic.

A P and ID is not normally drawn to physical scale.

A vessel shown beside a pump on the drawing might actually be fifty feet away in the plant.

The drawing explains how the system functions rather than exactly where every item is physically located.

Is a P and ID the Same as a Process Flow Diagram?

No.

A process flow diagram gives you the larger process picture.

It might show crude entering a separator, gas leaving overhead, liquid moving to another vessel, and products continuing through the facility.

A P and ID goes much deeper.

It shows the valves, instruments, piping connections, control loops, drains, vents, equipment tags, and many of the details required to operate and maintain that process.

A useful way to think about it is this:

A process flow diagram tells you what the process does.

A P and ID tells you how the process is connected and controlled.

Where Should a Beginner Start?

Do not start by trying to decode every symbol.

Start with one piece of equipment.

A separator is a good example.

Find the separator.

Now find the line entering it.

Trace that line backward.

Where does it come from?

Then trace the gas outlet.

Where does the gas go?

Trace the oil outlet.

Trace the water outlet.

Once you understand those main process paths, start looking at the equipment attached to them.

This is much easier than staring at the entire drawing and trying to understand everything at once.

Always Find the Drawing Legend

One of the biggest beginner mistakes is assuming every company uses symbols in exactly the same way.

Industry standards such as ISA 5.1 provide widely used instrumentation conventions, but individual projects can still have their own drawing practices.

The legend tells you what the symbols and line types mean on that particular drawing set.

Before guessing what a symbol represents, check the legend.

Experienced engineers and operators do this too.

How Do Equipment Tags Work?

Major equipment usually has an identification tag.

You might see something like:

V 101

P 201

E 301

K 401

The exact naming system depends on the facility.

A common convention is that the letter identifies the equipment type and the number identifies the individual item.

For example, P may be used for a pump.

V may identify a vessel.

E may identify a heat exchanger.

K may identify a compressor.

Do not assume those letters are universal.

Use the facility equipment list and legend.

Once you know an equipment tag, you can often use it to find maintenance history, operating procedures, data sheets, work orders, and other documentation.

How Do You Follow Piping on a P and ID?

Start with the main process lines.

Follow the direction of flow.

Some drawings use arrows to indicate flow direction. Other times you determine direction by understanding the process.

Do not assume that left to right always means normal flow.

As you trace the line, watch for:

Valves

Branches

Reducers

Check valves

Control valves

Instruments

Drains

Vents

Connections to other drawings

One line may disappear at the edge of the sheet with a reference telling you where it continues.

That reference is important.

The process did not end simply because the page ended.

What Does a Line Number Tell You?

Many facilities assign identification numbers to process lines.

The line identification can provide information about:

Pipe size

Service

Piping specification

Unit or area

Insulation

Sequence number

The exact format depends on the company.

A line number is more useful than it first appears.

If you are troubleshooting a leaking line or preparing equipment for maintenance, the line identification helps confirm that everyone is talking about the same pipe.

How Do You Recognize Valves?

A P and ID can contain many types of valves.

Common examples include:

Gate valves

Ball valves

Globe valves

Butterfly valves

Check valves

Control valves

Relief valves

Shutdown valves

A new operator does not need to memorize every valve symbol on day one.

Start with the valves that affect normal operation.

Ask:

Which valves isolate the equipment?

Which valve controls flow?

Which valve controls pressure?

Which valves are normally open?

Which are normally closed?

Where can trapped pressure remain after isolation?

That information is far more useful than simply memorizing shapes.

What Is a Control Valve?

A control valve automatically changes position to control a process variable.

For example, a separator may need to maintain a certain liquid level.

A level transmitter measures the level.

A controller compares that level with the desired value.

The controller then changes the position of the liquid control valve.

If level becomes too high, the valve may open farther.

If level becomes too low, it may close.

That is a control loop.

The P and ID lets you see the entire relationship on one drawing.

How Do Instrument Tags Work?

Instrumentation tags often use letters describing what the instrument measures and what it does.

Common first letters include:

P for pressure

T for temperature

F for flow

L for level

The letters that follow describe the function.

For example:

PT can mean pressure transmitter.

PI can mean pressure indicator.

PIC can mean pressure indicating controller.

LT can mean level transmitter.

LIC can mean level indicating controller.

FT can mean flow transmitter.

TT can mean temperature transmitter.

The loop number connects devices belonging to the same control function.

A pressure transmitter and pressure controller with the same loop number are normally associated with the same pressure control loop.

How Do You Read a Simple Pressure Control Loop?

Imagine gas leaves a separator.

The gas outlet pressure needs to remain near a desired operating pressure.

A pressure transmitter measures separator pressure.

The transmitter sends that information to the control system.

A pressure controller compares measured pressure with the set point.

The controller sends a command to a control valve.

The valve changes position.

If vessel pressure rises, the valve might open farther and allow more gas to leave.

If pressure falls, the valve might close somewhat.

That is the process logic hiding behind a handful of symbols.

Once you start reading loops this way, instrumentation becomes much easier to understand.

What Is the Difference Between an Alarm and a Shutdown?

An alarm tells someone that a condition requires attention.

A shutdown takes action.

Suppose a separator level is increasing.

The control system may first generate a high level alarm.

If level keeps rising, a higher level condition could initiate a shutdown to prevent liquid from entering downstream gas equipment.

The exact design varies by facility.

This is why you should distinguish between:

Normal control

Alarm

Trip

Shutdown

Relief protection

They serve different purposes.

What Does Fail Open or Fail Closed Mean?

Some automatic valves are designed to move to a defined position if their control energy is lost.

A valve may fail closed.

Another may fail open.

The correct position depends on what creates the safer process condition.

Imagine a fuel gas valve feeding a fired heater.

Loss of control energy may need to stop fuel flow.

Now imagine a cooling system where continued flow is needed to remove heat.

The preferred failure position could be different.

Never assume that every shutdown valve fails closed.

The process design determines the desired safe state.

Why Are Drains and Vents Important?

Beginners often focus on the large process lines and ignore the small connections.

Those small lines matter.

A vessel may need to be depressured.

A pump may need to be drained.

A high point may need a vent.

A low point may collect liquid.

A maintenance procedure may depend on connections that appear minor on the drawing.

If you are preparing equipment for maintenance, vents and drains can become some of the most important items on the P and ID.

What Does a Relief Valve Show You?

A pressure safety valve or relief valve protects equipment from excessive pressure.

On a P and ID, identify what equipment the valve protects and where the relief stream goes.

It may discharge into:

A flare header

A relief header

A vent system

Another safe disposal system

Do not confuse a relief valve with a normal pressure control valve.

Normal controls are intended to keep the process within its operating range.

A relief device provides protection when pressure exceeds allowable limits.

How Do Operators Actually Use P and IDs?

They are useful during much more than training.

Operators use them while:

Tracing lines

Planning isolation

Investigating abnormal pressure

Checking valve lineups

Preparing equipment for maintenance

Understanding control loops

Responding to process upsets

Reviewing modifications

Preparing for startup

Preparing for shutdown

A good field habit is to take a P and ID into the process area and physically trace the system.

Find the vessel shown on the drawing.

Find the inlet line.

Find the isolation valve.

Find the transmitter.

Find the control valve.

Then return to the drawing.

After doing that several times, the symbols begin connecting with real equipment in your head.

Why Can a P and ID Be Different From the Actual Plant?

Plants change.

A valve is added.

A line is rerouted.

An instrument is replaced.

A temporary modification becomes permanent.

A project is completed but the drawing update is delayed.

Good facilities control these changes carefully through engineering and document management systems, but discrepancies can still occur.

If the field installation and approved drawing disagree, do not casually decide which one is correct.

The discrepancy should be investigated through the facility’s established process.

What Should a New Operator Learn First?

Do not try to memorize the entire plant.

Choose one system.

Learn where the fluid comes from.

Learn where it goes.

Learn what determines pressure.

Learn what determines level.

Learn what causes flow.

Learn which valves isolate the system.

Learn what alarms protect it.

Learn what shuts it down.

Then move to the next system.

That is how complicated facilities eventually become manageable.

Frequently Asked Questions

What does P and ID stand for?

P and ID means piping and instrumentation diagram.

Is a P and ID drawn to scale?

Normally no. It shows functional relationships rather than exact physical location.

What is the difference between a P and ID and a process flow diagram?

A process flow diagram shows the main process. A P and ID provides much more detail about piping, valves, instruments, controls, and connections.

What do P, T, F, and L mean on instrument tags?

They commonly refer to pressure, temperature, flow, and level.

What is the best way to learn P and IDs?

Trace one process system at a time and compare the drawing with the actual equipment in the field.

Do all companies use exactly the same symbols?

No. Industry standards provide common conventions, but always use the legend for the specific drawing set.

Why are P and IDs important for operators?

They help operators understand process flow, controls, isolation points, instrumentation, alarms, and equipment relationships.

What is the biggest mistake beginners make?

Trying to understand the whole drawing at once. Start with one piece of equipment and follow one flow path.

Related Articles